■Expo-net:plastering method(floors) listed unit-price
|
|
(per 10m2)
|
unit:\
| |
class |
item |
volume |
unit |
@ |
amount |
| 1) |
materials
sum |
Expo-net
undercoat mortar
surface mortar
others |
10.00
10.00
10.00
1.00 |
m2
m2
m2
set |
9,800
750
3,250
3,000 |
98,000
7,500
32,500
3,000
141,000 |
| 2) |
labor
sum |
skilled worker
worker
machine hired
tools hired |
1.20
0.40
1.00
1.00 |
head
head
set
set |
28,000
18,000
2,000
1,000 |
33,600
7,200
2,000
1,000
43,800 |
| |
total sum |
|
184,800 |
|
| Conditions |
 |
Application scale should be more than 100m2.
Aggregate should be Kinka 7mm in size.
Above exclude cost for concrete forms, molding, jointing,
concrete, electricity, water and application in exceptional case.
|
|
|
 |