■Expo-sheet:plastering method listed unit-price
|
|
(per 10m2)
|
unit:\
| |
class |
item |
volume |
unit |
@ |
amount |
| 1) |
materials
sum |
Expo-sheet
mortar(1,2)
chemicals
others |
10.00
10.00
10.00
1.00 |
m2
m2
m2
set |
8,700
500
1,000
2,000 |
87,000
5,000
10,000
2,000
104,000 |
| 2) |
labor
sum |
skilled worker
worker
machine hired
tools hired |
1.20
0.80
1.00
1.00 |
head
head
set
set |
28,000
18,000
2,000
1,000 |
33,600
14,400
2,000
1,000
51,000 |
| |
total sum |
|
155,000 |
|
| Conditions |
 |
Application scale should be more than 100m2.
Aggregate should be Kinka 7mm in size.
Above exclude cost for concrete forms, molding, jointing,
concrete, electricity, water and application in exceptional case.
|
|
|
 |